Advanced Technology Center now 80 percent complete
Posted: June 29, 2015
With the Advanced Technology CenterĀ 80 percent complete, here’s what’s coming up in the next few weeks:
- Interior painting
- Storefront window wall installation
- Completion of brick installation
- Colored concrete installations
- Roof garden installation
Facilities and Operations Director Marty Mattes says substantial completion date is Aug. 20, with final completion set for Sept. 1. When construction completes, you can expect the following:
- Commissioning
- Broadcast furniture and equipment delivery, assembly and installation
- Program furniture and equipment delivery, assembly and installation
- IT network and computer installation setup and configuration
- Program relocations
- Occupancy and operations within the building